Click here to skip the navigationCity of Cupertino Logo.   Contact Us | Event Calendar | FAQ |  Recreation Schedule |  Site Map |  
City Government.  
About Cupertino.Cupertino Living.Doing Business.Just Visiting.City Government.  
  Home Page : City Government : Departments And Offices : Planning And Building : Development Activity : Under Construction : Development Activity Report  
City Council
Commissions
Committees
Agendas and Minutes
Departments and Offices


City Channel
Municipal Code
Publications List
Directory
City  Government Org Chart



    DEVELOPMENT ACTIVITY REPORT — SUMMER 2008
RESIDENTIAL PROJECTS

Approved But Not Built
  • Las Palmas
  • The Grove and Villa Serra Apartments
  • 21989 Lindy Lane
  • White Tiger Subdivision


  • Under Construction
  • Jyan-Ping Lily Chang
  • Varian Subdivision
  • Linnet Lane Subdivision
  • Oak Park Village (Former Santa Barbara Grill)
  • Rockwell Homes
  • Stelling Road Development at Orion Lane


  • Completed
  • Stelling Road Development at Orline Ct.
  • Stelling Road Development at Jollyman Lane


  • REPORT'S OTHER SECTIONS
  • Commercial Projects
  • Mixed Use Projects
  • City Projects



  • Approved But Not Built

    Las Palmas
    Location:
    West side of North Stelling Road, between Interstate 280 and Homestead Road.

    Developer: Los Gatos Trade Line Corporation
    Architect: Dahlin Group
    Project Manager: Gary Chao

    Application Summary:
  • Re-zoning of a 1.1-acre parcel from BQ (Quasi-Public) to P-Res (Planned Residential).
  • Tentative Map to subdivide a 1.1-acre parcel into 20 parcels and one common parcel.
  • Use Permit to construct 20 residential units (12 detached and 8 attached) on a 1.1-acre site (northwest corner of N. Stelling and I-280).
  • Architectural and Site approval to construct 12 small lot single-family residential homes and 10 attached town homes.


  • Project Data:
    Residential
    Lot Size: 1.24 acres
    Type: Detached Single-Family Residential and Townhomes
    Units: 10 Detached and 10 Townhomes
    Density: 16 units/acre
    Height: 30 feet
    Commercial
    Type: N/A
    Size: N/A
    Height: N/A

    Status:
  • The project was approved by the City Council on July 17, 2007, including but not limited to the following key conditions:
    1. - Applicant shall submit a landscape plan to be reviewed and approved by the Director of community Development.
      - A construction management plan shall be submitted to the City for review and approval prior to building and grading permit issuance.
      - Elements of the existing historical home shall be used to construct a trellis or gazebo structure at the common plaza area.
      - A $25,000 contribution shall be provided by the applicant for enhancement s to the pedestrian walkway along the west side of the N. Stelling Road bridge that crosses over Interstate 280.
      - New detached park strip shall be provided as part of the revised curb plan.
      - Applicant shall submit a green building design program to the City for review and approval prior to building permit issuance.
  • Building permits under review.
  • Site demolition work has commenced.
  • Construction anticipated to begin in the 3rd quarter of 2008.


  • Visual:
    Proposed Site Plan
    Conceptual Front Elevations


    The Grove and Villa Serra Apartments
    Location:
    North Stelling Road between Homestead Road and Interstate 280 at 10870 North Stelling Road.

    Developer: Prometheus Real Estate Group
    Architect: Christiani Johnson Architects
    Project Manager: Aki Honda-Snelling

    Application Summary:
    1. ARCHITECTURAL AND SITE APPROVAL to construct an additional 116 apartment units, a public park, a recreational facility, and leasing office within an existing apartment complex (Villa Serra/The Grove) for a total of 504 units.
    2. VARIANCE from the R3 (apartment) rear yard setback requirements.
    3. PARKING EXCEPTION from 2 spaces per unit to 1.74 spaces per unit.
    4. TREE REMOVAL for the removal of 92 trees and a replanting plan on a proposed modification to an existing apartment development.
    5. ENVIRONMENTAL DETERMINATION: Negative Declaration recommended. The project will have no significant, adverse environmental impacts.

    Project Data:
    Residential
    Lot Size: 25.43 acres
    Type: Apartments
    Units: 505
    Density: 19.86 units/acre
    Height: 30 feet
    Commercial
    Type: N/A
    Size: N/A
    Height: N/A

    Status:
  • The Project was approved by the City Council on July 3, 2007. Main discussions points are as follows:
    • Addition of 116 new apartment units, including 70 one-bedroom units and 46 two-bedroom units. The existing complex consists only of one and two bedroom apartment units.
    • Approximately 10,000 square foot Traffic Operations Center (TOC) to be relocated to adjacent area south of the existing location, with the applicant required to fully fund the relocation of the TOC, including relocating the existing shed structure and modular office, extending electrical and fiber optic cabling, and paying up to $50,000 for a new storage facility at the new TOC location to replace the existing storage container.
    • Franco Court width is to be retained at the current width (40 feet, curb-to-curb) and no parking will be permitted on Franco Court.
    • New .7 acre public park to be constructed on the southwest corner of Homestead Road and Franco Court.
    • Public Art will be installed.
    • Bike/pedestrian access only from Villa Serra to Franco Court; no driveway access will be permitted.
    • Retain 18 of the 92 trees proposed to be removed.
    • Provide a landscaped parkway treatment along Homestead and Stelling Roads.
  • Building permits have been submitted and are under review.
  • Site demolition work has commenced.
  • Construction anticipated to begin in the 2nd Quarter of 2008.
  • Park Commission reviewed the preliminary park design on February 7, 2008, April 2, 2008, and June 5, 2008 with the following recommendations:
    1. - Option A (the version without the half basketball court)
      - Use native plants (trees and shrubs) throughout.
      - Use ‘Green’ building/construction materials.
      - Incorporate a public restroom facility.
      - Pathways within the park shall consist of (semi-permeable) interlocking pavers subject to approval from the Director of the Public Works Department and San Jose Water (for pathway surrounding the pump area).
      - Add additional picnic tables in the northwest corner of the park.
      - Minimize the fence enclosure around the pump equipment to the maximum extent possible while meeting San Jose Water’s needs.
      - Delete 10 parking stalls along the west side of the park allowing the park area to expand.
      - Incorporate an entry for pedestrians on the southeast corner of the park.
      - Install plain wrought iron fencing around the perimeter.
  • City Council is scheduled to review the park design on August 5, 2008.


  • Visual:
    Proposed Floor Plan Elevation for Building Type 1
    Sample Elevation and Floor Plan

    Park Design<
    Park Design


    21989 Lindy Lane
    Location:
    North side of Lindy Lane off of Regnart Road.

    Developer: Frank Sun
    Architect: Westfall Engineers, Inc.
    Project Manager: Colin Jung

    Application Summary:
  • Tentative Map


  • Project Data:
    Residential
    Lot Size: 2.6
    Type: Single Family
    Units: 3 (1 existing, 2 proposed)
    Density: 1.2 dwelling units/acre
    Height: N/A
    Commercial
    Lot Size: N/A
    Type: N/A
    Size: N/A
    Height: N/A

    Status:
  • Tentative map was approved by the City Council on December 6, 2005.
  • Final Map was approves by City Council on July 3, 2007.


  • Visual:
    Tentative Site Plan


    White Tiger Subdivision
    Location:
    Along the south side and approximately 100 feet west of the terminus of Greenleaf Drive.

    Developer: Greenleaf Associates
    Architect: Sarah Robinson, Architect
    Project Manager: Gary Chao

    Application Summary:
  • Tentative Map to subdivide a .95 acre parcel into four lots ranging from approximately 6,430 square feet to 8,880 square feet, plus a remainder lot of 11,500 square feet
  • Use Permit for three, two-story single family residences in a planned development zoning district
  • Architectural and Site Review to construct three, two-story single family residences in a planned development zoning district


  • Project Data:
    Residential
    Lot Size: .95
    Type: Single family lots and existing California Water Service well l
    Units: 3
    Density: 3 dwelling units/acre
    Height: 28 feet maximum
    Commercial
    Lot Size: N/A
    Type: N/A
    Size: N/A
    Height: N/A

    Status:
  • The Building Permits have been issued.
  • Construction is underway.


  • Visual:
    Site Plan
    Site Plan

    Sample Elevation
    Sample Elevation

    Site Photo
    Site Photo


    Under Construction

    Jyan-Ping Lily Chang
    Location:
    10121 Pasadena Avenue

    Developer:Jyan-Ping Lily Chang
    Architect: Marius E. Nelsen, Nelsen Engineering
    Project Manager:Piu Ghosh

    Application Summary:
  • TENTATIVE MAP to subdivide a 9.750 square foot parcel into two 4,875 square foot parcels.
  • ARCHITECTURAL and SITE REVIEW for two, two-story 2,193 square foot single family residence.
  • USE PERMIT to construct two, two-story 2,193 square foot single family residence.


  • Project Data:
    Residential
    Lot Size: 0.22 acres, 9,750 square feet
    Type: Residential
    Units: 2
    Density: 8.9 dwelling units/acre
    Height: 30 feet allowed (Project Max = 28 feet)
    Note: These homes will be two of the first green homes built in Cupertino
    Commercial
    Type: N/A
    Size: N/A
    Height: N/A

    Status:
  • Approved by Planning Commission on November 13, 2007.
  • Building permits approved February 2008.
  • Construction is underway.


  • Visual:
    Proposed Site Plan
    Proposed Site Plan


    Varian Subdivision
    Location:
    East side of Crescent Road at the terminus of Crescent Court.

    Developer: Kelly Gordon Development Corporation
    Architect: Memarie Assoc., Inc.
    Project Manager: Piu Ghosh

    Application Summary:
  • Subdivision


  • Project Data:
    Residential
    Lot Size: Approx. 10,000 to 13,000 square feet
    Type: Single Family Residential
    Units: 5 lots
    Density: 2.4 dwelling units/acre
    Height: N/A
    Commercial
    Type: N/A
    Size: N/A
    Height: N/A

    Status:
  • Approved by the Planning Commission on August 8, 2006.
  • Approved by the City Council on September 19, 2006.
  • The Final Map and Improvement Plan were accepted by City Council on March 30, 2007.
  • The project has obtained Planning Approval for four of the five homes.
  • Three of the five homes have received a certificate of occupancy.


  • Visual:
    Site Plan
    Site Plan

    Site Photo
    Site Photo - Lot 1

    Site Photo
    Site Photo Lot 2

    Site Photo
    Site Photo Lot 3

    Site Photo
    Site Photo Lot 4

    Site Photo
    Site Photo Lot 5


    Linnet Lane Subdivision
    Location:
    East side of Linnet Lane, at the southern terminus.

    Developer: Frank Ho
    Architect: Studio 61
    Project Manager: Piu Ghosh

    Application Summary:
  • Architectural and Site Review to construct four 2,185 square foot single family residences
  • Use Permit to construct four 2,185 square foot single family residences
  • Tentative Map to subdivide a 22,647 square foot parcel into four parcels ranging from 4,575 to 5,247 square feet


  • Project Data:
    Residential
    Lot Size: 0.52 acres
    Type: Townhomes
    Units: 4
    Density: 17.69 units/acre
    Height: 25 feet 3 inches
    Commercial
    Type: N/A
    Size: N/A
    Height: N/A

    Status:
  • The Project was recommended for approval by Environmental Review Committee on April 11, 2007
  • The Project was approved by Planning Commission on April 24, 2007.
  • The building permits have been approved.


  • Visual:
    Proposed Site Plan
    Proposed Site Plan

    Sample Elevation
    Sample Elevation

    Site Photo
    Site Photo


    Oak Park Village (Former Santa Barbara Grill)
    Location:
    10745 N. De Anza Boulevard, southwest corner of Highway280 and De Anza Boulevard

    Developer: Pinn Brothers
    Architect: Dahlin Group
    Project Manager: Gary Chao

    Application Summary:
  • Rezoning of a 1.37 acre parcel from P(CG, ML, Res 4-10) to P(CG, ML, Res 35)
  • Subdivision Map to create 45 residential units
  • Use Permit to demolish a vacant restaurant building and construct approximately 46 units.
  • Architectural and Site Review to construct 46 residential units.


  • Project Data:
    Residential
    Lot Size: 1.6 acres
    Type: Condominiums
    Units: 46
    Density: 29 dwelling units/acre
    Height: 45 feet
    Commercial
    Type: N/A
    Size: N/A
    Height: N/A

    Status:
  • Approved by City Council February 2, 2005.
  • Project exterior, surrounding landscaping and public art are complete.
  • Project nearing completion.


  • Visual:
    Site Photo
    Site Photo


    Stelling Road Development at Orion Lane
    Location:
    West side of Stelling Road at Orion Lane

    Developer: Pan Cal Development
    Architect: Steve Yang & Associates
    Project Manager: Gary Chao

    Application Summary:
  • Single Family Design Review


  • Project Data:
    Residential
    Lot Size: 7,500 to 13,000 square feet
    Type: Detached Single Family Residence
    Units: 5 lots
    Density: 4 dwelling units/acre
    Height: 28 feet maximum
    Commercial
    Type: N/A
    Size: N/A
    Height: N/A
    Status:
  • Approved on November 28, 2006 by the Director of Community Development.
  • The project is underway.


  • Visual:
    Site Plan
    Site Plan

    Site Photo
    Site Photo

    Site Photo
    Site Photo


    Rockwell Homes
    Location:
    East side of Stevens Canyon between St. Andrews Avenue and Riverside Drive.

    Developer: Rockwell Homes
    Architect: Steve Yang & Associates
    Project Manager: Vera Gil

    Application Summary:
  • Rezoning
  • Subdivision
  • Use Permit
  • Architectural and Site Review


  • Project Data:
    Residential
    Lot Size: 1.5 acres
    Type: Multi-family Attached Town Homes
    Units: 15 (12 market rate town homes/3 below market units)
    Density: 10 dwelling units/acre
    Height: 28-29 feet
    Commercial
    Type: N/A
    Size: N/A
    Height: N/A

    Status:
  • Approved by Planning Commission on December 13, 2005.
  • Approved by City Council on January 3, 2006.
  • Building plans approved November 14, 2006.
  • The project is nearing completion.


  • Visual:
    Site Photo
    Site Photo


    Completed

    Stelling Road Development at Orline Ct.
    Location:
    Northwest corner of Orline Court and Jollyman Lane.

    Developer: Shashi, LLC.
    Architect: Studio 61
    Project Manager: Piu Ghosh

    Application Summary:
  • Subdivision Map to subdivide 0.47 acres into 2 parcels, ranging from 7,387 sq. ft. To 7,390 sq. ft.
  • Single Family Design Review.


  • Project Data:
    Residential
    Lot Size: Approximately 7,000 to 8,000 square feet
    Type: Detached Single Family Residence
    Units: 2 units
    Density: 4.17 dwelling units/acre
    Height: 28 feet maximum
    Commercial
    Type: N/A
    Size: N/A
    Height: N/A

    Status:
  • Approved by Planning Commission on November 22, 2005.
  • Final Map was approved by the City Council on January 16, 2007.
  • The project is complete.


  • Visual:
    Site Photo
    Site Photo

    Site Photo
    Site Photo


    Stelling Road Development at Jollyman Lane
    Location:
    Northeast corner of S. Stelling Road and Jollyman Lane.

    Developer: Shashi, LLC.
    Architect: Studio 61
    Project Manager: Piu Ghosh

    Application Summary:
  • Subdivision Map to subdivide 0.47 acres into 2 parcels, ranging from 7,387 sq. ft. To 7,390 sq. ft.
  • Single Family Design Review


  • Project Data:
    Residential
    Lot Size: 0.47 acres
    Type: Detached Single Family Residence
    Units: 2 units
    Density: 4.26 dwelling units/acre
    Height: 28 feet maximum
    Commercial
    Type: N/A
    Size: N/A
    Height: N/A

    Status:
  • Approved by Planning Commission on November 22, 2005.
  • Final Map was approved by the City Council on January 16, 2007.
  • The project is complete.


  • Visual:
    Site Photo
    Site Photo

    Site Photo
    Site Photo


    REPORT'S OTHER SECTIONS